Welcome to Module 4, Installation
Qualification, or IQ.

2
00:00:04.579 --> 00:00:09.357
We continue with the fictional V-201 oral-
liquid mixing vessel.

3
00:00:09.477 --> 00:00:12.650
The design review described what was
intended.

4
00:00:12.770 --> 00:00:16.908
Now the team compares the installed system
with the accepted

5
00:00:17.028 --> 00:00:19.786
design and manufacturer recommendations.

6
00:00:19.906 --> 00:00:24.941
Every identifier and observation in this
module is invented for training.

7
00:00:25.061 --> 00:00:27.621
No real equipment has been qualified.

8
00:00:28.241 --> 00:00:31.551
A drawing shows a temperature sensor
connection.

9
00:00:31.671 --> 00:00:36.292
A walkdown identifies which sensor is
installed at that connection.

10
00:00:36.412 --> 00:00:40.895
An operational challenge examines how the
assembled loop behaves.

11
00:00:41.015 --> 00:00:43.291
These answer different questions.

12
00:00:43.411 --> 00:00:47.549
Finding the correct tag does not
demonstrate alarm response,

13
00:00:47.669 --> 00:00:52.910
and a successful alarm test does not
repair missing material identification.

14
00:00:53.030 --> 00:00:57.168
Keep each conclusion tied to the evidence
actually obtained.

15
00:00:57.788 --> 00:01:01.926
For our case, the installation boundary
includes the vessel,

16
00:01:02.046 --> 00:01:04.819
agitator, outlet components, instruments

17
00:01:04.939 --> 00:01:07.146
and defined utility connections.

18
00:01:07.266 --> 00:01:11.335
The upstream utility plant has its own
qualification scope.

19
00:01:11.455 --> 00:01:14.766
Record where one system ends and another
begins.

20
00:01:14.886 --> 00:01:19.782
A qualified water system does not
automatically prove that a new branch

21
00:01:19.902 --> 00:01:24.523
has the correct connection or that its
delivered water is suitable.

22
00:01:25.143 --> 00:01:28.591
The teaching conclusion is limited to
installation

23
00:01:28.711 --> 00:01:31.953
evidence reviewed against the defined
baseline.

24
00:01:32.073 --> 00:01:35.107
It is not permission to manufacture a
batch.

25
00:01:35.227 --> 00:01:39.572
Operational and performance verification
remain separate needs.

26
00:01:39.692 --> 00:01:43.140
Where stages are combined in an approved
approach,

27
00:01:43.260 --> 00:01:47.053
the underlying evidence questions still
remain visible.

28
00:01:47.173 --> 00:01:50.070
Your first activity separates installation

29
00:01:50.190 --> 00:01:53.776
observations from claims that require
later studies.